Course Code: sapmrpone
Duration: 14 hours
Course Outline:
DayTopicsStart TimeEnd TimeDuration in min
Day1MRP - Process Flow上午 9:00:00上午 10:30:0090
 Q&A and coffee break上午 10:30:00上午 10:40:0010
 MRP - Process Flow - continued上午 10:40:00下午 12:10:0090
 Q&A and lunch break下午 12:10:00下午 1:10:0060
 MRP-relevant Master Data - Lot sizes, planning calendar, planning times下午 1:10:00下午 2:40:0090
 Q&A and break下午 2:40:00下午 2:50:0010
 MRP Run (MD01/MD02) - Control parameters下午 2:50:00下午 3:50:0060
 Q&A下午 3:50:00下午 3:55:005
 Planned order conversion and adjustments - production order, purchase requisition and purchase order下午 3:55:00下午 5:25:0090
 Q&A下午 5:25:00下午 5:30:005
Day2Production Planning Master Data - BOM, Routing, Scheduling time上午 9:00:00上午 10:30:0090
 Q&A and coffee break上午 10:30:00上午 10:40:0010
 BOM - usage of alternative BOM components上午 10:40:00上午 11:10:0030
 Q&A and break上午 11:10:00上午 11:15:005
 Production Order - ATP check on components, checking groups, checking rule, missing part report上午 11:15:00上午 11:55:0040
 Q&A and lunch break上午 11:55:00下午 1:00:0065
 Detailed Scheduling Board下午 1:00:00下午 3:00:00120
 Q&A and break下午 3:00:00下午 3:10:0010
 New MRP features introduced in S/4Hana - MRP live, DDMRP, PMRP下午 3:10:00下午 5:10:00120
 Q&A下午 5:10:00下午 5:15:005